Round ten and a half months of alternative site visitors and diversions have come to an finish: on Sunday the necessary railway line between Hamburg and Berlin launched alongside its complete size. The primary long-distance practice to Berlin is scheduled to start out at Hamburg Central Station at 5:34 a.m. – and is scheduled to achieve town in lower than two hours. Regional trains have already been working earlier than, as Deutsche Bahn (DB) introduced.
What passengers must find out about resuming the route:
What’s the significance of the connection?
Lengthy-distance, regional and freight trains run for round 280 kilometers between the nation’s most populous cities. In long-distance transport, Berlin-Hamburg is taken into account crucial direct connection between two cities. Earlier than the overall renovation, round 30,000 passengers traveled on the long-distance route on daily basis, together with many commuters.
What’s going to change for passengers after the renovation?
From Sunday onwards, the long-distance trains will run once more on the regular half-hourly intervals, and the regional trains will run once more on the standard traces. Till the top of the month, long-distance trains should run extra slowly in sections as a result of expertise remains to be being examined. The railway expects that each renovation will make the general community extra steady. “This has an impression on general punctuality.” A alternative bus service will likely be discontinued.
Is it true that journey time will increase?
As soon as the renovation is accomplished, the scheduled journey time for the ICE will improve by two minutes to 107 minutes. The change solely applies to this 12 months’s timetable. A railway spokeswoman stated that the trains may journey quicker than deliberate. In accordance with her, the truth that the journey time is longer is because of the truth that there are extra trains on the highway than earlier than. It is like being on the road. If there are a whole lot of automobiles on the highway, individuals drive extra slowly.
Why was it renovated?
In accordance with the railway, the route was closely used and subsequently closely worn. Earlier than the renovation, a mean of round 470 trains traveled on the route on daily basis. Earlier than the overall renovation started, the railway rated the situation of the route as 3.7. After the renovation, the DB predicted a grade of two.3.
When did the overall renovation start?
The undertaking started on August 1, 2025. The plan was to finish the renovation by April 30, 2026. The railway justified the truth that the renovation was accomplished round a month and a half late due to the frost originally of the 12 months. Staff had been unable to dig cable shafts and work on overhead traces was made tougher. The railway reopened a primary part in mid-Might, and since then trains have been working constantly between Hamburg and Schwerin once more.
What has been renewed?
Amongst different issues, the railway changed tracks, switches and alerts and modernized 28 stations. The employees renovated bogs and climate shelters and arrange bicycle racks. At a number of stations, platforms have been lengthened in order that longer trains can method them.
What’s lacking?
The digital practice management expertise ETCS, which the European Union needs to grow to be commonplace, can’t be used even after the renovation. Nonetheless, the railway has made preparations for a later use. “Gear with ETCS will happen within the early 2030s,” the railway stated. ETCS permits trains to journey nearer collectively on a route. There was criticism of the railway’s choice to not set up ETCS opposite to the unique plan.
How a lot does the overall renovation price?
It was deliberate that the railway must increase 2.2 billion euros. The state-owned transport firm didn’t present a brand new sum upon request. The ultimate price dedication will solely be made after the development work has been accomplished, the DB stated.
What had been the impacts for passengers?
In long-distance site visitors, trains had been rerouted through Stendal and Uelzen. There have been additionally fewer trains and the journey time elevated by round 45 minutes. The results had been extra extreme on regional transport: trains had been canceled or solely ran partial routes. The railway used a alternative service with greater than 200 buses. At instances there was a dispute between the bus supplier Ecovista and the railway as a result of buses had been older than agreed and there have been breakdowns.
What was the impression on the financial system?
The freight railway affiliation complained about disadvantages through the renovation. “If I shut a route, the diversions must work,” stated an affiliation spokeswoman. “That didn’t work effectively on this case.” Some different routes weren’t sufficiently upgraded, and short-term development websites and disruptions to the infrastructure on the diversion routes typically led to a number of hundred kilometers of detours.
Will different routes be renovated?
The overall renovation is a part of the high-performance community hall renovation infrastructure undertaking introduced in 2022. Greater than 40 routes are to be renewed by the mid-2030s, in order that no extra development will likely be crucial there for round 5 years. The work started in 2024. First, the “Riedbahn” Frankfurt-Mannheim was renovated, adopted by the Emmerich-Oberhausen connection, which is necessary for freight site visitors.
What renovations are coming subsequent?
In accordance with plan, 4 additional common renovations are to be accomplished this 12 months – on the Hagen-Wuppertal-Cologne, Nuremberg-Regensburg, Obertraubling-Passau and Troisdorf-Wiesbaden routes.
© dpa-infocom, dpa:260612-930-210930/1